FEDERAL MINISTRY OF POWER, WORKS & HOUSING

FMPWH

Font Size
Welcome To Federal Ministry Of Power Works And Housing
The Power Sector
The Works Sector
The Housing Sector
Power Works And Housing

LATEST PRESS
17 July, 2018

Third Mainland Bridge To Be Shut For Three Days For Assessment

* Three-day closure begins from July 27 while repairs begin after report of assessment is received to determine extent of deterioration
* “We will try to reduce the period of closure as much as possible. But this is ultimately a choice between peoples’ safety”, says Fashola
* “There was a signed statement from my office and it did not contain 27 months”, he maintains

The Third Mainland Bridge in Lagos will be closed to traffic for three days from July 27, 2018, for investigative work to be conducted to assess the current condition of the Bridge, the Minister of Power, Works and Housing, Mr. Babatunde Fashola SAN, has explained in Abuja.

Fashola, who spoke, Monday, as Guest on the Channels Television breakfast programme, Sunrise Daily in the Federal Capital Territory, said the shutdown was necessary in order to ascertain whether there had been any material deterioration between the period the first procurement for maintenance of the Bridge was approved and now adding that the three days would be used “to really do an examination just to be sure that there has been no material deterioration beyond what we procured”.

The Minister, who debunked the misreporting in some sections of the media that the Bridge would be closed for 27 months, declared, “The first message we sent out was that it was going to be closed for three days from the 27th of July”, adding that the duration of maintenance would only be determined after the report of the investigative work has been received and extent of deterioration known.

He said the investigation would have been carried out earlier but the need to reduce the inconveniences that would accompany the closure compelled government to shift the time to a more convenient period when children would be on vacation and when fewer vehicles were likely to be on the Bridge.

“We thought that if we allowed the children to go on vacation first it would reduce the number of vehicles that needed necessarily to be on the road and ultimately reduce the amount of inconvenience. But now we are torn between maintenance and safety and peoples’ convenience”, Fashola said adding, “Essentially the first three days at the end of this month, as issued in our Press Statement, is for investigative work to be conducted to assess the current condition”.

The Minister, who said it was only after the assessment of the amount of maintenance work involved that government engineers and the contracting firms would lay out the plan of work, added, “I think it is later in the year or early next year that the repairs will then start”, pointing out that some of the equipment and materials have to be imported.

Noting that the repairs would “imminently compel some closure”, Fashola, who recalled that the Bridge had been closed for repairs in the past when he was Governor, pointed out that it was shut down for 12 weeks, adding, “We will try to reduce the period of closure as much as possible. But this is ultimately a choice between peoples’ safety; that bridge must not collapse and it needs maintenance”.

“It has been built now going up to a period of 30 years and if you recall, the maintenance that was done at that time was not completed because the budget was cut and that was why they did it in phases. So we are back to what we should have done before. It is costing more but it needs to be done”, he said.

Reiterating that he was currently not in the position to say how long the maintenance would last until the receipt of the report from the investigation and the amount of damage determined, declared, “For now, the first three days is what I can speak of and it is when we get the report and determine the extent of damage that we will now come back to the public and tell them and say definitively how long it will be”.

“I am not in the position to say it now until that report comes back to us. But what will happen at the end of July is three days”, he said, adding that those peddling the 27 months rumour about the duration of repairs might have mistaken the “July 27th” date mentioned in the government Press Statement for 27 months. “There was a signed statement from my office and it did not contain 27 months”, he said.

Fashola, who admonished the Media, both traditional and social, to endeavour to be more accurate in their reportage especially of such sensitive issues, expressed regrets that many of the nation’s public assets have remained unmaintained for decades citing the Ijora Bridge which he recalled collapsed some time ago due to lack of maintenance after 40 years plus.

Housing Is A Catalyst For Development And Sustainable Economic Growth Says Fashola The Minister of Power, Works and Housing, Babatunde Raji Fashola, SAN, has said that the present Administration has taken leadership role by demonstrating how provision of affordable housing can catalyze development and sustainable economic growth in Nigeria. Fashola explained that President Buhari has used the National Housing Programme (NHP), presently active in 34 States of the federation in the last three years, as one of the tools to grow the economy and extricate the nation from recession.   According to him, ‘’we are able to employ, on the average, a thousand people at each of the 34 NHP sites, and this is only for the pilot stage’’. The Minister stated this at the recently concluded 7th Meeting of the National Council on Lands, Housing and Urban Development held at the Banquet Hall, Gombe International Hotel, Gombe State with the theme ‘Provision of Affordable Housing: A Catalyst for Development and Sustainable Economic Growth’. Speaking at the Council, Fashola urged Policy Makers and government at all levels to make efforts in consolidating on the achievements of the present government by building more houses and also proffer policies to address urbanization. He said that one of such policies is to consciously redistribute wealth and opportunities by strong commitments to programs like Agriculture and Mining. The Minister stated that from his trips across the nation, ‘’I can tell you categorically that President Buhari’s investment in infrastructural development is impacting on the nations urbanization challenge in a positive way’’. In his remarks, the Special Guest of Honour and the Host Governor, the Executive Governor of Gombe State, H.E. Alhaji Ibrahim Hassan Dankwambo, commended the Ministry for choosing Gombe State as host, assuring that the Council meeting was bound to address the challenges facing Land Administration, Housing and Urban Development to enable the sector contribute meaningfully to the socio-economic development of the nation. Dankwambo stated that access to quality and affordable housing is not only fundamental to the health and well being of families and communities, but critical to human survival. He urged Government at all levels to work assiduously in ensuring provision of affordable housing, particularly for the low and modest income earners in the country. While he commended the efforts of the Federal Government in the construction of mass housing under the National Housing Programme (NHP), stating  that the state government has also consolidated on these gains with the construction of over  1, 000 housing units, fully completed and allocated to civil servants and the general public in the state. Earlier, while addressing the meeting of the Permanent Secretaries at the state level and other stakeholders, the Permanent Secretary of the Ministry, (Works & Housing) Mohammed Bukar, said that the provision of affordable housing rest on the shoulders of all stakeholders in the industry, adding that ‘it is a collective duty to provide leadership for achieving the set objective’. Bukar enjoined all stakeholders to make judicious use of the opportunity provided by the 7th Meeting of the National Council on Lands, Housing and Urban Development to deliberate on the memoranda submitted for consideration towards formulating and strengthening policies that will address the challenges in the built environment and making housing affordable to all Nigerians. In her goodwill message, the Head of the Civil Service of the Federation, Mrs Winfred Oyo-Ita, represented by the Permanent Secretary, Service Welfare, Mrs Didi Walson Jack, stated that the Council meeting is an auspicious moment bringing together key stakeholders in the housing sector to deliberate on policy issues geared towards the full delivery of mass housing. She commended the ministry for initiating and promoting the discuss on affordable housing in Nigeria According to her, the Federal Executive Council in consideration of the need to reposition the civil service for greater productivity approved the Federal Civil Service Strategy and Implementation Plan, adding that one of the 8 goals of the Plan is to enhance the value reposition of Civil Servants via improving their access to affordable housing. She stressed that this initiative led to the creation of the Federal Integrated Staff Housing (FISH) programme by the Head of Service, which has assisted over       35, 000 civil servants to acquire homes through the provision of mortgage with a long term repayment plan. The Council meeting ended with the issuance of a Communiqué unanimously agreed by all stakeholders to chat the way forward and also formulate a holistic Housing Policy for development and sustainable economic growth in Nigeria. A total number of Thirty-four (34) memoranda were received and considered under the following four thematic groups: i.                     Policy, Finance, Capacity Building for Affordable Housing Delivery; ii.                   Building Consideration and Institutional Strengthening for Affordable Housing Provision; iii.                  Urban Planning Provision for Affordable Housing; and iv.                 Lands and Infrastructure Consideration for Affordable Housing.
16 July, 2018
FEC Approves Reconstruction Of Roads In The Country The Federal Executive Council (FEC) presided over by President Muhammadu Buhari on Wednesday approved N35.6billion for reconstruction of roads and bridge in the country. The Minister of Power, Works and Housing, Mr Babatunde Fashola, disclosed this when he briefed State House correspondents at the end of the Council’s meeting held at the Presidential Villa, Abuja. The Minister said N8.9 billion of the amount was approved for construction of Ikom bridge and road in Calabar, Cross River. According to him, the road and bridge has a completion period of 24 months and when completed, will create access to the port for trailers to move freely with their containers. The Minister said that N11.78 billion was approved for Nguru –Gashua – Balmari road in Yobe State, while N8.6 billion was approved for Ilorin – Kishi road in Kwara State. He said the Council also approved N5.4 billion for another road project in Abia State, He disclosed that N933 million was also approved for automatic meter reading equipment for Transmission Company of Nigeria (TCN). “The other project that was approved relates to power and this is the approval to procure at the request of the TCN an automatic meter reading machine and services – that will include the installation of equipment and also the training of engineers, auditors, IT engineers who will operate and maintain the system. “The total installation period is 18 months, supply and installation,’’ he said. According to Fashola, the wholesale meters are different from the retail meters, saying that smooth implementation of the wholesale meters would help in dispute resolution as data can be easily produced online and eliminate all delays in the system. The Minister of Information and Culture, Alhaji Lai Mohammed, who fielded a question on the controversy surrounding NYSC exemption certificate of the Minister of Finance, Mrs Kemi Adeosun, said the federal government had already responded to the allegation via statement from the NYSC. He said: “The government has spoken. NYSC is part of government and I have nothing to add to what the NYSC has said.’’
12 July, 2018
Act To Make Discos Deliver On Responsibilities To Consumers, Fashola Directs NERC *Minister asks NERC to enforce DisCos meter supply contract, improvement on their distribution equipment, capacity to take more powers from GenCos *Also directs NBET to work with BPE to improve DisCos collection remittance and  pay their debts to help promote stability in the Sector *Says complaints coming to Government over metering, estimated billing and mass disconnections cannot continue *I remain convinced that privatization is way forward- FASHOLA The Minister of Power, Works and Housing, Mr. Babatunde Fashola SAN, Monday directed the Nigerian Electricity Regulatory Commission (NERC) to immediately step in to ensure that Electricity Distribution Companies (DisCos) improve on their distribution equipment and increase capacity to enable them optimize the use of electrical resources by the Generation Companies (GenCos). Fashola, who spoke at a Press Briefing on the “Power Sector State of Play, Next Steps and Policy Directives”, also directed NERC to enforce the contract of DisCos to supply meters and act to ensure the urgent speedy supply and installation of meters with a view to eliminating estimated billing and promote efficient industry and market structures. The Minister, who said the improvement in their distribution equipment and increase in capacity would enable the DisCos take up the available 2,000MW difference between the generation capacity of the GenCos and the distribution capacity of the DisCos, also directed the Regulatory Commission to stop DisCos from threatening private entrepreneurs from entering the market to supply consumers whom they are unable to supply. Instead, according the Minister, such entrepreneurs should be licensed by the Commission subject to its terms and conditions “in order to promote competition and private sector participation and avoid a private monopoly of power”, adding that as clearly stated in Section 71(6) of the Electric Power Sector Reform Act (EPSRA) dealing with Terms and Conditions of licenses, “no exclusivity or monopoly was intended for a license holder such as GenCos or DisCos”. The aforementioned Section states that, “Unless expressly indicated in the license, the grant of a license shall not hinder or restrict the grant of a license to another person for a like purpose and, in the absence of such an express indication, the licensee shall not claim any exclusivity, provided that the commission may allow a licensed activity to be exclusive for all or part of the period of the license for a specific purpose, for a geographical area, or for some combination of the foregoing”. Noting that the Regulatory Commission has not issued any such exclusive license to any DisCo, Fashola declared, “If we take into consideration that, after five years of privatization, there are still people and businesses who do not have power or enough power, common sense and public interest demands that we must not resist ordinary people, small businesses like shops and markets from seeking alternative sources of energy”. “The truth is that they already have these sources of alternative energy, in small petrol and diesel generators that cost them about N100 per kilowatt hour. If the DISCOs are not resisting the generator sellers who are contributing to pollution, what is the logic of resisting small entrepreneurs bringing mini gas plants to supply a market need?”, the Minister argued, pointing out that for now, the nation’s developmental needs could not wait “for businessmen who are not yet ready to serve”. Urging NERC “to act with dispatch”, Fashola said the stated policy statements were made in the National interest, public good, the need to support small businesses, provide access to power for ordinary people and increase productivity adding, however, that although he was not unmindful of concerns about loss of market or customers by DISCOs such concerns must be balanced against national interest and that with improvement in their businesses, they would be in a position to use their economies of scale of large volumes of power to buy out or out-price the small entrepreneurs. The Minister implored members of the public who seek more information “to get a copy of EPSRA and read its simple provisions”, adding that the Act confers extensive regulatory powers on NERC “including the power in Sections 73 and 74, to amend or cancel a license if the licensee is unable to discharge  the duties and obligations imposed by the license”. Fashola also directed NBET, the bulk trader, to work with Bureau of Public Enterprises (BPE), to fashion out ways to ensure that the DisCos improve their collection remittance and also start to pay their debts saying this would help to promote stability in the Sector. “This business cannot progress if debtors do not pay their debts”, he said. Stating, however, that it is neither his intention nor that of Government to take over the business of the DisCos, the Minister declared, “On the contrary, it is Government’s desire to see DISCOs thrive and flourish in a competitive environment”, adding, “In the period when they are not yet ready, willing, or able, life must go on and we must find solutions and substitutes as we have seen in other sectors”. Such sectors, he said, include the Broadcasting, Newspaper and Telecommunication Sectors where, according to him, “those who could not compete conceded and left the stage gloriously without breaking down the system”, while those who could compete have brought better living conditions to Nigerians. Saying that the policy directives should not be seen as anti-Privatization, Fashola, who said they were meant to ginger all stakeholders to brace up to their responsibilities to serve the people, added, “I remain convinced that Privatization is the way forward. Privatization has brought us mega value in Broadcasting; it has brought us better value in Newspapers, Telecommunications and Banking and other sectors of our national life and I remain convinced that it will deliver in Power”. “This is not a time to trade blames, because there is enough to go round; rather it is a time to reiterate everybody's responsibility and urge all of us to brace up, to do what we are obliged to do, which is to serve the people, he said, adding, “I suspect that these facts may appear like a red flag to the bulls of anti-privatization, but I remain convinced that privatization is the way forward”.       Recalling that when the public complained about the tariff approved by NERC, he was the one that stood in the forefront of explaining to the public even though it was the Discos who collect the tariff, Fashola declared, “In the face of this picture, where we have power to sell, with more to come, the number of complaints coming to Government for meters, which the DISCOs should supply, and for estimated billings, and mass disconnections when not everybody is owing, cannot continue”. “Government must act, and will do so. The DisCos bought these assets with their eyes opened, and they must compete to deliver or exit”, Fashola declared, adding that Small businesses who need very little power are not getting enough because the DisCos could not take the power to them. The Minister expressed dismay that investment of GenCos was threatened because they could not utilize the capacity they have installed, adding that in order to improve service to small businesses, Government, acting through the Rural Electrification Agency (REA), was linking Small Power Entrepreneurs with markets like Ariaria in Aba, Sabon Gari Market in Kano, and Sura Market in Lagos which, according to him, contain approximately 37,000, 13,000, and 1,047 shops respectively, which are being metered by the small entrepreneurs who have offered to replace the generators of traders with more efficient power and meters. According to the Minister, there are 15 markets in all which if successfully implemented would provide power to 85,485 shops, empower 205,000 SMEs and create 2,000 jobs during the installation and after in operation and maintenance adding, “The DisCos are agitating that this should not happen, yet they offer no solution.” On what government has been doing to assist the DisCos and other operators to deliver power, Fashola said as facilitator of business and enabler of the Private Sector government had, through the Central Bank of Nigeria, made available the sum of N213 Billion to the Power Sector at a concessionary interest rate, below market rate, to GenCos and DisCos adding, however, that some DisCos had shied away from taking the facility. According to him, “Probably because of the source of fund conditions, such as opening of letters of credit attached to the performance, some DisCos have not taken the money”, adding that currently  NERC detected “an unauthorized use of money by the Ibadan DisCo” and was now taking some remedial measures. The Minister said Government has also responded to claims of debts owed by Ministries, Departments and Agencies (MDAs) of government to DisCos before the present administration, a debt which, he said, “was alleged to be in the region of over N70Billion adding that at the cost to government, “several hundreds of thousands of bills, amounting to about 450,000 bills, were verified” while government has ascertained that N27 Billion was owed by Federal MDAs to DisCos. Prior to the tenure of this administration, he said, GenCos and Gas suppliers who produce power, were being underpaid by NBET because the DisCos were under collecting or under-remitting such that GenCos were getting only about 20 per cent of their invoices from Power adding that Government intervened and created N701 Billion Payment Assurance Guarantee (PAG)  to NBET to ensure that payment to GenCos improved. Payment of invoices, according to Fashola, has now increased from 20 to 80 per cent “in the hope that if we move production, DisCos will collect and remit”. He expressed regrets, however, that his office still receives daily reports by mail, letters and e-mails of exorbitant bills by DisCos to Consumers without meters while the remittance by DisCos to NBET has not increased resulting in NBET  owing the GenCos N325.7 Billion, a debt which he was certain could be settled if NBET could collect what DisCos are currently owing it. Also, in order to assist in the evacuation of 2,000MW, the difference between what the GenCos can produce and the DisCos can distribute, Fashola said the DisCos were asked to submit their transformer and other equipment requirements adding that, as part shareholders, government has committed to invest N76 Billion for the procurement of equipment and installation to help the DisCos evacuate the 2,000 MW to consumers. Other inputs by government, he said, include settling an inherited court case and making available N37 Billion to Meter Asset Providers (MAPs), under the regulations made by NERC to license meter investors, “to help supply meters that the DisCos are under contract to supply but are yet unable to do so”, adding that the gesture was in order to bridge he metering gap and to promote harmonious relationship and reduced friction between the DisCos and their MAPs. Progress, the Minister said, have also been recorded in the sector between 2015 and 2018 including improvement in the generation of power from 4,000 MW (approx) in 2015 to 7,000 MW (approx) in 2018 averaging an increase of 1,000 MW (approx) per annum adding that additional 455 MW (Azura); 215 megawatts (Kaduna), 240 MW (Afam III); 40 MW (Kashimbilla); almost totaling 954 MW would be added this year while 700 MW (Zungeru), 480 MW (Okpai II) about 1,150 MW are projected for 2019, even as the GENCOs are undertaking various repairs, rehabilitation and expansion that would bring on incremental power. “Transmission has also increased from 5,000 MW (Approx) in 2015 to 7,124 MW (Approx) in December 2017 averaging 1,062 MW per annum increase in transmission capacity. TCN currently has about 90 Transmission projects in various stages of construction and many are to be completed this year”, Fashola said adding, “So, we can transport what the GENCOS generate and there is a Transmission Expansion plan 2018 to 2028 which Government is committed to implement”. The Minister said although distribution has increased from 2,690 MW (Approx) in 2015 to 5,222 MW (Approx) in 2018, averaging an increase of 844 MW per annum “because the DISCOS have also done some work”, adding that from 2016 when the DisCos complained about lack of enough power to distribute, the problem today was that the DisCos could not distribute all of the Power that was available, leaving the sector with an unused capacity of 2,000 MW (Approx), with the approximately 1,150 MW projected to come this year and 2019. In the robust question and answer session that followed, Fashola explained that all the solutions being applied to reform the power sector such as the Payment Assurance Guarantee, among others, were contained in the Power Sector Reform Programme (PSRP) which the his Ministry compiled urging stakeholders, including the Media, to read it for understanding. Also present at the event were the Minister of State, Power, Works and Housing Surveyor Suleiman Zarma Hassan, Chairman NERC, Professor James Momoh and his Vice, Engr. Sanusi Garba, Managing Director, Transmission Company of Nigeria, Mr. Usman Gur Mohammed, Managing Director Rural Electrification Agency, Mrs. Damilola Ogunbiyi, other Agency Heads, Directors and Special Advisers .
10 July, 2018
Records 1 to 4 of 130
PUBLIC ANNOUNCEMENT
20 May, 2018

Multinational: Benin, Cote D’ivoire, Ghana, Nigeria And Togo And The Economic Community Of West African States (ECOWAS)

Study on the Abidjan – Lagos Corridor Highway Development Project

Notice for Expression of Interest

Recruitment Of A Consultant To Conduct A Corridor Economic & Spatial Development Initiative Scoping And Project Packaging Study For The Abidjan-Lagos Highway Corridor Highway Development Program

The ECOWAS Commission has received Grants from the African Development Fund (ADF) and the European Development Fund (through the African Investment Facility –AfIF) to cover the cost of studies on the Abidjan-Lagos Corridor Highway Development Project, and intends to use part of Grant amount to finance service Consultants Contract for Corridor Economic & Spatial Development Initiative (SDI) Scoping and Project Packaging Study for the Abidjan-Lagos Highway Corridor.

The services under this Contract mainly consist of: (i) defining the corridor’s zone of influence to show direct and indirect beneficiaries (populations, other economic activities, etc.) which the corridor affects and vice versa, using the appropriate technical methodology under the SDI concept; (ii) identifying and analyzing the significant developmental aspects of the various zones along the corridor; (iii) identifying a longlist of economic projects (trade, logistics, industry, etc) within the geographical zone of influence of the Corridor, that are worth developing as part of the multinational highway project to result in a holistic economic development corridor, (iii) data gathering, and scoping (shortlisting) of SDI projects; (iv) developing regulatory and institutional framework for the holistic development of the corridor as an economic development corridor; (v) perform economic and financial analysis of selected projects to determine the nature of investments required for further development and (vi) develop an Abidjan-Lagos corridor economic development investment & marketing plan.

Feasibility and Detailed Engineering Studies are to be conducted per the following lots to cover the entire corridor: (i) Lot 1: Abidjan (Cote d’Ivoire)-Takoradi (Ghana), 295.3 km; (ii) Lot 2: Takoradi-Apimanim  (Ghana)-Accra (Ghana)–Akanu/Noepe Border (Ghana), 466 km; and (iii) Lot 3: Akanu (Ghana)-Noepe (Togo)-Lome (Togo)-Agonmey Glozoun (Togo)-Athieme (Benin)-Cotonou (Benin)-Seme-Krake (Benin/Nigeria)-Lagos (Nigeria), 320.06 km.  All distances provided are indicative and could be more depending on the eventual confirmation of alignments by Member States. 

The overall duration of the Feasibility and Detailed Engineering technical studies is estimated at twenty seven (27) months for each lot and the Corridor Economic and Spatial Development Study shall cover the entire corridor for a period of twelve (12) Months with some interim outputs (impacts from shortlisted projects) that could be taken on board by the feasibility and detailed design Consultants.

The ECOWAS Commission invites Consultants (firms with proven experience in spatial development initiatives, economic corridor development, urban and land use planning, transport infrastructure engineering firms for large-scale infrastructure projects) to submit their candidacy for the services described above. Interested, eligible and qualified consultants must produce information on their ability and experience demonstrating that they are qualified for services of similar nature. The shortlisting criteria shall be: (a) general experience in Economic Corridor Development, urban planning and development services (Studies, Technical Assistance, Project Management,) over the last ten (10) years; (b) specific experience in the field of studies of spatial development and establishment of economic zones along multinational highway corridors during the last ten (10) years; (c) Specific experience in cross-border or multinational land-use planning over the past ten (10) years; (d) availability of key personnel (list, qualification, experiences); (e) logistical and equipment; (f) IT Resources and specialized software, etc. (g) capacity to produce reports and all other relevant documents on the study in English and French.

NB: Each reference will be summarized on a project sheet, and will be considered only if the candidate attaches supporting documents indicating the contact information of the contracting authorities so as to facilitate verification of the information provided: Excerpts of contract (inner cover page and page with the signatures) plus Attestation of good performance.

Consultants may form groups to increase their chances of qualification.

The eligibility criteria, the preparation of shortlist, and the selection procedure shall comply with the African Development Bank’s Procurement Framework for operation funded by the Bank Group as of October 2015 available on the Bank’s website: http://www.afdb.org. The selection procedure will be based on Quality Based Selection Method (QBS), and a shortlist of six (6) firms which present the best profiles shall be drawn up after the expression of interest. Also the firms that are part of an international network are to submit one expression of interest.

Interested consultants can obtain further information at the e-mail addresses mentioned below during working hours: 8:00 a.m. to 12:00 noon (local time) on working days: procurement@ecowas.int with copy to pgueye@ecowas.int; vtulay@ecowas.int; cappiah@ecowas.int ; deklu@ecowas.int ; sbangoura@ecowas.int

Expressions of interest must be delivered in a written form (one (1) signed original plus four (4) copies) in (person, or by registered mail) to the address below, not later than 14th June, 2018 at 11:00 a.m. (GMT+1), Nigerian Time, and must be clearly marked: “Studies on the Abidjan-Lagos Corridor Highway Development Project/Expression of Interest in Consulting Services for Corridor Economic and Spatial Development Initiatives Study”.

For delivery in person or by registered mail to:

Directorate, General Administration, Procurement Division
First (1st) Floor of the ECOWAS Commission Headquarters,
Plot 101, Yakubu Gowon Crescent,
Asokoro District, Abuja,
NIGERIA.

Requests for further information or clarification could be sent by e-mail:
Attention : Commissioner General Administration &Conference
Email : vtulay@ecowas.int

with copies to :

* sbangoura@ecowas.int
* procurement@ecowas.int
* cappiah@ecowas.int
* pgueye@ecowas.int
* deklu@ecowas.int

The working languages shall be English and French. The Expression of Interest will be submitted in English.

OTHER NEWS
31 May, 2018

Abeokuta Substation Gets New 60MVA Transformer To Improve Electricity

The yearning to ensure qualitative and stable power to Nigerians has made the Federal Government to upgrade the 132/33KVA Abeokuta Transmission Substation with the installation of a new 60 Mega Volt Ampere (MVA) capacity transformer to boost electricity supply in Abeokuta and its environs.

Addressing the Minister of State II Power, Works and Housing, Surveyor Suleiman Hassan Zarma, who was on an inspection tour to the substation recently, the Assistant General Manager Transmission, Papalanto Sub – Region of the Transmission Company of Nigeria (TCN), Engr. Adeonipekun Adesina said the transformer upon its complete installation would complement the three existing ones at the station.

According to him, the station has 3 transformers of 30MVA each, making a total of 90MVA. But with the new one, the station will now have a 150MVA wheeling capacity.  “It used to be a 90MVA Substation. But with the introduction of the new transformer, there will be more power to deliver to the masses and there will be steady supply of electricity”, Adeonipekun said.

Adeomipekun disclosed that the transformer when energized, would improve power supply to Abeokuta Township, Imeko, and Lagos Road, part of Sagamu and University of Agriculture, Abeokuta. In his address, the Minister re-affirmed the Federal Government’s commitment to increasing power supply in the country. Saying “the Federal Government is investing in the expansion of transmission capacity through the TCN by building more substations and expanding existing ones”, adding that the transformer which is installed by the Transmission Company of Nigeria (TCN), under the National Integrated Power project (NIPP) of the Federal Government is aimed at driving the industries, boosting the economy, creating employment opportunities to our teaming youth in Abeokuta and the country in general.

Records 1 to 1 of 15
Speeches
25 August, 2017

Mr Babatunde Raji Fashola, SAN At The 6th National Council On Land, Housing And Urban Development

I welcome you all very warmly to this 6th meeting of the National Council on Lands, Housing and Urban Development.

I am enthused to speak to you because of the progress we have made from our last meeting in 2016 in Ilorin, Kwara State.

My enthusiasm derives from simple but very profoundly impactful things that we committed to do last year in Kwara and which we have done.

The first is that we resolved to facilitate the use of Exchange of letters for the Transfer of title to land when states are transferring land to the Federal Government.

I am happy to report that there has been very inspiring compliance based on the several letters of exchange that I have received and which I have duly signed.

All I need say about this in terms of compliance is that if there is still any state yet to comply they should please do so very quickly.

This is an important matter to report to the public. It shows that we do not gather at this Council just to talk. It shows that we have the capacity to act. It shows that change is possible when people commit themselves and that Governments in Nigeria can get things done.

The other matter that enthuses me, is the progress report on our National Housing Programme about which I briefed this Council last year.

At the time of the Council meeting in August 2016, I reported that we were finalizing designs to accommodate our cultural, climactic and other diversities and that when the designs were completed we would commence construction to pilot the designs and test them for affordability and acceptability.

I am pleased to report that construction has started in 33 states where land has been made available.

This is fulfilment of another commitment made at last year’s council by at least 90%.

This must give a lot of hope to our people that this Government will do what it says, and I want to thank all the states who gave us land, the staff of the Ministry who have worked hard to drive the programme, and the Honourable Minister of State, Mustapha Baba Shehuri who has been visiting and inspecting project sites.

I have myself made whistle stop visits to our sites in Taraba, Gombe, Ekiti, Oyo, and what I saw demonstrates to me very clearly how impactful the National Housing Programme has been, even at the pilot and inception stage.

The bricklayers I met in Taraba, Gombe and Ekiti, Rilwanu Adamu and Abubakar Umar, who asked me to thank President Buhari, for putting them back to work, the owners of the cement mixer in Oyo who said that his  equipment has been idle for 2 years but was now earning N20,000 daily on our site in Oyo.

And of course, Mr and Mrs Emmanuel, a builder and caterer respectively who live in Lagos, but who now find dignity, labour and employment at our Oyo site, by participating in building and food supply.

And this brings me to the theme of this year’s Council meeting which is “Building for Inclusion, Growth and Prosperity”.

Yes, it is true that we have a National Housing deficit, and while some choose to engage themselves by discussing about the size of the deficit, we choose to engage ourselves by doing something about the deficit.

This is because, every building we start and ultimately complete is a blow to the size of the deficit which no amount of talk can inflict.

We understand that every nation has a housing deficit and the bigger the size of the population, the size of the growth rate and the size of the urbanization rate, the bigger the size of the deficit.

But while we commit to the National policy of delivering affordable housing, we must look at short, medium and intermediate streams of opportunities for employment, productivity, skill development, restoration of dignity of our people which lie within the housing delivery value chain.

This is consistent with one of the Pillars of the Economic Theory and Growth Launched by President Buhari, which is “investing in our people.”

Apart from the artisans that I have spoken about, it might interest you to also know that 653 contractors were engaged in the pilot scheme to deliver 2,736 units. A total of 54,680 people were employed in the process.

The opportunities for inclusion will include masonry, electrical, plumbing, welding, supplies of materials, transportation and many more.

Our desire is to multiply these opportunities this year and beyond.

One of the directives that I have given to our staff is to review the procurement requirements and guidelines in consultation with our legal department, to ensure that we open the opportunities for participation.

Yes, I understand the need to get value for money and the processes that have been put in place by previous administrations to guide procurement.

The question we must ask ourselves then is whether we have truly saved money and whether we have developed?

On the evidence that is available, the country has clearly made more money from oil sales in the last decade that cannot be accounted for by way of project delivery and infrastructure development.

But if this was not enough problem, the procurement requirements then limits the amount of advance payment Government can pay to 15% and sets conditions that overlook the level of literacy of the vast majority of our people and the nature of small businesses that they run.

My experience in the last 20 months is that small businesses have difficulty complying with our procurement process and this requires not only policy reviews as I have ordered, but also legislative intervention by parliament.

This is one of the actions we must take to fulfil the objectives of the theme of this Council so that we can build for inclusion, for growth and for prosperity.

While our National Housing Programme, is the first of its type on a National scale in many decades that seeks to respond to the deficit, government agencies such as the Federal Mortgage Bank, Federal Housing Authority are being repositioned to play their role more effectively to address the Housing problem.

For example, the Federal Housing Authority has been mandated by the ministry to reposition herself to be one of our champions of housing delivery based on her previous track record.

Similarly, the Federal Mortgage Bank continues to deepen participation in the National Housing Fund which forms a reliable pool of funding from which she lends money to contributors by way of mortgage loans to acquire houses.

In addition, the bank has granted loans to estate developers to build houses; and from their recent report to me, they currently have 3,823 housing units available for sale in various states of the Federation.

The ministry has directed that these units, their prices, description, location and eligibility criteria be widely publicized in transparent offers to Interested members of the public.

The next level of intervention which the ministry is developing is the use of co-operatives.

This is very important to the theme and purpose of this year's Council meeting which centers around inclusion.

Our experience has shown that very sizable parts of our population who are productive and self-employed have been excluded from formal processes that regulate access to Funding, land or housing.

However, these large number of people operate successfully by themselves, in groups which they form as co-operatives to protect their common interests and pursue their developmental objectives.

Co-operatives have been very prolific and successful in sectors like agriculture and market organizations where the vulnerability of an individual is transformed into the strength of a group.

Our Government sees no reason why the successes of co-operatives in these sectors cannot be utilized to facilitate housing delivery, access and inclusion.

We are determined to place the might of government at the disposal of groups who can form themselves into co-operatives, as enabling capacity to acquire the land, take loans, build for themselves and operate a rent to own policy for those who cannot pay full ownership cost at start.

When our work on the review of the existing laws, and the processes for eligibility are completed, we will undertake a national launch and enlightenment program to kick the active use of co-operatives in housing delivery.

I have chosen to speak about this plan at this meeting because the success of this initiative will depend on what is done at state level; and many, if not all, states are represented here.

Your readiness and willingness to give land to well constituted cooperatives will be a critical determinant to success and inclusion.

So, this serves as notice for you to start thinking ahead about what your respective states can offer to the initiative.

Before I conclude, I will like to go back to the issue of the deficit in housing and set the context, not only how it has grown with our size but also why some seem so terrified of approaching it.

When we started this national housing program, my attention was brought to the fact that there had been no national housing program since the end of the second republic in 1983, which is about 34 years ago.

I must of course not be mistaken for saying that there were no housing interventions. There were. But they were neither sustained nor were they implemented on a national scale.

This omission is a big contributing factor to the size of the deficit and the exclusion of people.

Of course, there has always been a National Housing Policy, which seeks to deliver affordable housing, but as I said there is no program to implement and actualize the policy.

This government has now formulated that national program by concept, design and now pilot stage implementation which in the early stages has already created opportunities for 653 contractors, and created 13,680 direct jobs and 41,000 indirect jobs.

What we must do therefore is to repeat this program year on year, not only at federal level but also at state level.

Ladies and gentlemen, if we do this and also successfully implement the housing cooperatives, leverage private sector capacity, strengthen FHA and FMBN to play their roles, we will be creating a housing economy that will irreversibly and positively transform our nation forever.

Not only will we be addressing one of the problems of urbanization, we will unleash the capacity to build for inclusion, for growth and prosperity.

In this way, the size of the deficit of housing will become an economic opportunity to immense proportions rather than a social burden to be scared of.

Thank you very much for your attention.

Babatunde Raji Fashola, SAN
Honourable Minister of Power, Works and Housing

Thursday 24th August 2017

Records 23 to 23 of 23
Photo News
10 July, 2018

FASHOLA BRIEFS THE PRESS ON THE STATE OF PLAY IN THE POWER SECTOR NEXT STEPS AND POLICY DIRECTIONS

Hon Minister of Power Works Housing Mr Babatunde FasholaSAN middle Minister of State Surv Suleiman Zarma Hassan right and Permanent Secretary Power Engr Louis Edozien left during the HonMinisters Press Briefing onthe State of Play in the Power Sector Next Stepsand Policy Directions at the Ministry of PowerWorks Housing Headquarters Mabushi Abuja on Monday 9th July 2018

Click To View More Pictures

Power News
Photo News
14 July, 2018

7TH NATIONAL COUNCIL ON LANDS HOUSING AND URBAN DEVELOPMENT HELD AT GOMBE STATE

Alh Ibrahim Hassan Dankwambo Governor of Gombe State Center Minister of Power Works and Housing HM Babatunde Fashola SAN right and the Deputy Gvernor Gombe State Hon Charles Iliya

Click To View More Pictures

4Th National Council On Power (Nacopp)
Records 1 to 2 of 40 Download(s)